Sunday, November 11, 2007

Ridge beams...



With the three portal frames now in place (which, by the way, fitted perfectly!) the end of last week saw the the central ridge beams lifted in place to tie the portals together at their apex and of course form the centreline of the roof against which will be fixed the rafters.


The ridge beams is made from mltiple bonded laminations of wood ('glu-lam') and is as strong as it looks! It's nice to see the height of the house now and easier to imagine how the 1st floor rooms will look.


This coming week work will start on installing the first floor joists, 1st floor walls and gables, so things should really start to take shape soon. Last but not least, a letter came though from the Enery Savings Trust at the weekend with the grant offer for the heat pump, which in Scotland is 30% of capaital cost up to a maximum of £4k; every little helps!

No comments: