Monday, June 16, 2008

Building Control Certificate




Last Wednesday the joiner returned to fit this to the large upper floor window and on Thursday building control visited and all completion certificate and paperwork were handed over. Another key landmark in the creation of the house. The window illustrated is a fixed light 1.8m x 1.8m and affords a stunning view. We were so disappointed to be advised that this would need an internal barrier in place to comply with building regs. If we had known then perhaps a different design or different specification might have been created in the first place. Looks like a play pen.




BT have failed to meet four appointments to connect the phone. OK they pay compensation of £10 each time but we'd really rather have a phone line. So hopefully order number 5 will work...........




The wonders of nature never cease to soothe, we have an abundance of brown hares who are particularly visible in the early morning

Tuesday, May 27, 2008

The pile of top soil which was created at the start of the contract has been levelled and will return to grass over time. We haven't delineated the garden/field boundary formally yet but will do so over the summer. We've asked Allan who built the long drystone wall on the east side to undertake various jobs over the next few months and the new garden wall will be part and parcel of that package of work. We've still got plenty of sandstone left from the old house to reuse. Since this picture was taken the hens have a had a field day (in the precise sense of the words) with the newly turned soil.
When the render was being cast one area fell off and was redone with the adjacent wall (on this picture to the left) within a couple of days but it is very clear where there is a variation in colour. The product is from K Rend and we've asked the architect to speak with their rep to see how this can be remedied. The wet dash finish is very typical of this area and much of Scotland. Variations between batches of the same colour can be a problem in a number of areas be they render, paint or other finishes but for us its very noticeable on this elevation.

On the snagging list for the window supplier - the paint on the aluminium cills is dropping away at a fair rate. Thankfully the maintenance man from the supplier came here last week, remedied a number of problems and are going to replace the damaged cills. The cause of the problem appears to be unknown so we hope the issue will not return with the new ones.

Wednesday, May 14, 2008

We are in!

No news is good news..and also reflects the lack of an internet connection.

We are in! Hurrah. The recent glorious weather has provided the best of starts with the sunshine emphasising how fabulously light this house is right through to late evening. Its not properly dark for many hours in this part of the world as we approach midsummer so the changing light outside is a constant delight.

Lots of building info to convey but the detail will have to wait a few more days, as will photos. Time and attention is devoted to our business and family needs at present. Unpacking is a slow process but we have everything we need. Having lived in a caravan for 9 months it is clear that our lives don't need most of the 'stuff' we have packed away in boxes so there's no urgency in that area. We've been concentrating on making sleeping and eating areas comfortable.

Quick info for today's blog;
1. We are SO pleased with our house. Satisfaction and feel good factor is high.
2. The quality of the architecture and the build is superb.
3. 3 points to resolve for building control i) one step on the patio is of a different height to others, ii) lashing eyes are to be provided for a window cleaner to clean the large first floor bedroom window and iii) on the same window there is ongoing discussion whether an internal barrier/rail needs to be put in front of the window - its a fixed light but the building control officer is considering this point, more later on that
4. Externally we live on a rather rough looking plot - plenty of work in the years ahead.
5. The apple trees are in blossom and look stunning.
6. The poorly hen has recovered completely and the hens are completely free range now that the chances of being run over have diminished. About 5 eggs per day are being produced.
7. The temperature in the house is pretty even despite it being hot outside and the MVHR is at its lowest setting.
8. The slate floor is particularly terrific in terms of appearance.
9. There is some snagging but not much except relating to the windows which have a good number of small issues to resolve. The supplier is currently proving slow to deal with them despite our first contact being around 2 months ago now.
10. Phone line being connected on Friday allegedly.

Saturday, March 29, 2008

The ideal low energy house?


What we've set out to do at ECF is to build a house which will use 70% less energy than one built to current building regulations. Its timber frame construction detailing hasn't wavered too far from the 'norm' to present any major problems for a timber frame kit manufacturer, decent building contractor or building control, and the costs of going this 'extra mile' haven't been excessive to the extent that they will be paid back within a decade in terms of reduced energy costs.

In essence, we have built to a standard which is accessable now by most contractors and self builders which is around 5-6 yrs before its time if the UK Government is to fully implement its Code for Sustainable Homes (CSH) strategy, on which this building should come in at around 3-4 on a scale of 1-6. There is clearly some distance to go from this to 'zero carbon', so what represents the 'optimum' for 'Level 6 living', the magical zero carbon level required by 2016 for all new homes?


Well, the same principles apply, namely...



  • building orientation to maximise solar gain in winter, spring and autumn whilst avoiding overheating in summer

  • high levels of insulation around the entire building envelope

  • high levels of airtightness coupled with heat recovery ventilation

  • highly insulated and well sealed doors and windows

...but for CSH level 6 the wall insulation would need to be increased to >300mm (from our 200mm), roof insulation to >450mm (from our 350mm) and windows to be triple glazed krypton filled units with insulated frames and glazing spacers (vs. our argon filled double glazed units). This would result in a building which could feasibly rely on the heat given off by its occupants and collected though its windows to keep it at a comfortable temperature without having to introduce a heating system. Construction might rely on internal masonry/concrete walls to store heat and keep a steady internal temperature, with the insulation fixed to the outside of this.


On the face of it quite simple, but a seriously long way from what the UK housebuilding industry is used to. Roll on 2016.....there is a lot of catching up to do and mindsets to be re-programmed.



Wednesday, March 26, 2008

Earth Hour

I've spent part of this evening contributing to a National Park meeting on renewable energy and sustainable building design and feel quite fired up on the whole subject. I came home, had a great discussion with Steve (before he went to Ikea for late night house shopping), then watched Grand Designs revisited about an underground house which essentially didn't need heating even in winter.

The whole debate about 'eco' and 'sustainable' is massively involved. We have built a well insulated, airtight, timber frame house with a thermal mass of 40 tonnes of concrete in the foundation slab to keep the internal temperature stable - that's great from an energy efficiency perspective, but is that scale of concrete usage a good thing, not least as the production of cement is an energy intensive process? Someone somewhere could maybe establish the whole life cycle energy equation.

Energy efficiency is a very important part of sustainability but I'm not sure if I can get my head around all of the issues. We've got fantastic argon filled double glazed windows with 'u' values of 1.4 (standard windows being between 1.8 and 2.0) and they are from Norway 'cos the Scandinavians having been building sustainable houses for years but ideally we should be buying UK produced windows in order to minimise transportation and support home industries...but it couldn't be done remotely near the cost as they would be regarded as 'one-offs' and 'specials'.

Anyway that's nearly enough...I looked at another blog this eve which prompted me to tell you about Earth Hour whereby you switch off your electricity at 8pm this Saturday for one hour. Its one of those experiments in activism which last year saw the city of Sydney reduce its 'leckie load by 10% thus illustrating the impact of individual actions. See the vid at http://www.youtube.com/watch?v=UcHz6Jv4l-g

Thursday, December 20, 2007

Wind and watertight for Christmas!



Yesterday we reached a major milestone with the delivery of the patio doors and main entrance door - the building was made wind and watertight and we now need a key to get in! This means that first-fixes and roughings can continue whatever the weather and the building is drying out nicely inside.


I've been working away from 'home' the last few days which has been frustrating, not least as there are many questions on detail items to deal with. I caught up after a half hour tour round this morning and it's clear that things are really moving on.

First fix electrics and plumbing are nearly all complete, with a few adjustments to make to the underfloor heating in the first floor bathroom and en-suite. Electrics are also nearly there with a few outstanding decisions to make on light switch locations and cooker load (ie. what cooker are we going to install!). The other first fixes remaining are the Heat Recovery Ventilation system ducting, TV/Satellite, phone, DAB (weak signal area for digital radio so need an aerial) and Cat 5 cabling.

Last but not least the slaters are making good progress and the stainless steel chimney for the wood stove looks superb, especially as the installation has been reinforced from the inside thus avoiding the need for external stays which might have spoilt the roofline.


Saturday, December 15, 2007

Saturday morning

Its just turned 9am on Saturday and we've taken a further delivery of Pavatherm Plus insulating board so the joiners can finish off the external insulation layer. There was relatively little activity on site yesterday as we were waiting for this delivery and the sliding door sets (3 off). The latter is now likely to be next week, but apparently has arrived from Penrith. I think these are around 6 weeks overdue and it's dissappointing that the windows from Norway arrived some four weeks ago and are now installed having been ordered at the same time as the patio doors! The main front door is also late and is sourced from Sweden.
The other happening this morning relates to the lame hen. Although it had a couple of better days in the past week it has now gone lame in both legs and is incapable of independent movement. So we had to wring its neck. I thought I could do this yesterday when it probably needed to be done but hen started clucking at me and I just couldn't so now that Steve has returned from working away he did the deed this morning. No, we're not eating it. There's no meat to speak of anyway but as we're not sure what's wrong with it it seems the best move....anyone with greater knowledge please advise!
We've got a fox prowling around. I need to repair/replace a bit of wire at the bottom of the gate to the hen pen before we go out this morning. There are fox prints on the top of the nesting box and on the roof of the hen house so we need to be sure to lock up quickly at dusk.I wonder if that explains the dead hares and rabbit the other week although I thought there would be more damage to the prey?
Rural living!......... we're off to Edinburgh today to see Santa, reindeer, lights, ice sculptures etc.

Thursday, December 13, 2007

Lots of trades on site.

The underfloor heating folk have been here today. We are not having any heating upstairs except for underfloor heating in the 2 bathrooms. This will be served by the ground source heat pump as per the ground floor, albeit in trays rather than embedded in the concrete as they are on the ground floor. As the first floor is laid the guys have to work from the underside of that floor, I can't imagine that's easy but they seem to be managing just fine.
The 6 joiners who are here are covering various tasks - the exciting one for us is seeing the main first floor picture window being framed out. A number of adjustments have been made to this but it is now looking good. Inside the first stages of first floor interior walls are being established; the children have already decided which 'bedroom' is theirs by virtue of which windows they have adopted.
There are lots of issues we are trying to resolve - the wrong cladding being one. More on that later...
Weather report - its positively balmy here today. I think we are becoming so hardy and acclimitised that we don't realise its December.

Monday, December 10, 2007

One Week On







Can't believe we haven't posted anything since last Tuesday....however its because so much has been happening on site. Aside from that we're very busy at home and work.


Saturday late afternoon we had our first snow of the year and there was a fair blizzard that evening. As usual at this elevation it thawed rapidly on the ground but the hills look fabulous. We have beautiful pink skies this morning - ideal for the slating to start today. Since last Monday the whole roof has been sheeted with sarking board, most of the windows are in place, the site has been tidied up, some scaffolding taken away, decisions on finer design detail made.



We had very wild weather and the joiners were on the roof a lot - it was so windy, wet and cold last week which was not pleasant at all.






Here's a few photos.............more news later.

Thursday, November 29, 2007

Roof progress & problems

Since last week when I mentioned that it hadn't rained much it has of course chucked it down most days this week! Ironically we had no water for most of yesterday as there was a burst water main somewhere on the west side of Loch Lomond which is a good distance from here.
Even the joiners finished early yesterday as they were soaked to the skin but this was also around the time that Steve and I realised/believed that some of the roof windows were not in the positions we had expected/designed. We arranged for the architect to visit site this morning....


The main problem was with the vertical position of the two main bedroom windows and the ensuite window, in that when standing up and viewed out from the inside, they are below level of vision! This is made even worse by the fact that the soffits from the top of the window frame are set square to the window (as shown in the photo above), which appeared to be an error that had crept into the final tender drawings. We were keen to resolve this asap as the sarking board is to be fitted next week with slaters booked the week after, and thus the opportunity will soon be lost (forever) to make adjustments.

Discussion on site with joiner and architect largely sorted the problem with an agreed plan to set the three offending windows higher in the roof, and an amended detail on the upper soffits to bring them closer to the horizontal as intended. As an aside, our joiner rightly cautioned this latter detail to ensure that sufficient insulation space is allowed for between soffit and sarking to avoid cold bridging and even condensation.

The view right is from the top of the scaffolding looking back to our 'trailer park' and some of the farm buildings. The office roof is just visibile to the right of the caravans.

Rather wierdly in the last week we've found 2 dead hares and a dead rabbit in different places around the steading area but none of them appear to have any injuries.....

Monday, November 26, 2007

Up on the Roof

Since last week's blog progress has been slow but steady. The roof is quite involved and various references have been made back to the timber frame manufacturer and the strucural engineer during the course of the week. To an extent it appears to be over-engineered (but I'm only a surveyor!) We employed a structural engineer to undertake much of the design as this was meant to save time with the timber frame manufacturer; I'm not sure this has been achieved and certainly the cost seems to be a good chunk higher. If we did this again we would handle this aspect differently but 'it is what it is'. The gloom of some dreich November days don't help and I'm beginning to hate the small cold caravan bathroom!!




On the plus side - the house is looking fabulous, we love the creation of the structure and its a pleasure to show people around. Our ever professional builder has put 3 additional joiners on site today to help get the roof structure finished. The first delivery of windows arrived last Friday and we bought the majority of the contents of the 3 bathrooms last week. The pavatherm external insulation is late but hopefully on its way, we've been chasing that delivery today. There's always something to do, as well as the day job which pays the bills. Last week we received the first interim certificate and invoice.



The photos were taken on Friday 23rd, illustrating the late Autumn sunshine at 8.30am; good light levels falling on the east elevation of the house (top photo). It was still below freezing as we'd had -4degC that night; but the views are glorious. The piccie above right is of the dining area, with its 3.5m ceiling height and lovely big window and door openings. The photo below is the view from this room to the north/northwest.

Friday, November 2, 2007

Daily Changes

The two joiners erected much of the ground floor on Monday and Tuesday which has been really exciting. Its terrific to see the rooms take shape and we are really pleased with the size of the window openings, particularly as we spent a long time last winter working through that element of the design. The joiners can't progress further until the steel arrives, this is delayed but due next Wednesday. In the meantime the scaffolders have been taking delivery of their kit and today have erected scaffolding on the west and south elevations. This photo is taken through the caravan window.


By and large we've had good weather since the start of the build, it is very mild at present which makes life comfortable for early mornings in the caravan.....however the past 2 days weather have included a large amount of rain and the area at the back of the house is somewhat muddy. Thankfully the caravans are on a concreted area.



Final photos today - 2 days collection of eggs and a piccie of Dora; generally the hens are laying 4 eggs per day which is quite good I think for ex battery hens and for the time of year. We've no idea if some hens are not laying at all but those that are have been using the nesting boxes. At this time of year with the daily reduction in light levels we can expect them to lay fewer eggs but at the moment our hens seem quite consistent.